Program Budget | Funds Promised | Funds Transferred |
---|---|---|
300,000 ARB | 300,000 ARB |
Grantee | Proposal Milestones | Estimated Date | % Completed |
---|---|---|---|
RWA Research - Helping Builders & Users | Rough Documents & High-Level Content | August 26, 2024 | 100 |
RWA Research - Helping Builders & Users | Progress on Detailed Write-Ups | September 13, 2024 | 100 |
RWA Research - Helping Builders & Users | Final Reports | September 23, 2024 | |
RWA Research - Helping Builders & Users | Final Presentations & Webinars | September 30, 2024 | |
Frictionless | Deployment on Arbitrum | September 3, 2024 | 100 |
Frictionless | Issuance on Arbitrum | September 3, 2024 | 100 |
Frictionless | Arbitrum-Avalanche Bridge | September 30, 2024 | |
Frictionless | Marketing Rollout | September 30, 2024 | |
Arbitrum RWA Analytics Dashboard - PYOR | Project Specification & Feedback | August 26, 2024 | 100 |
Arbitrum RWA Analytics Dashboard - PYOR | Building Phase Check-In 1 | September 13, 2024 | 100 |
Arbitrum RWA Analytics Dashboard - PYOR | Building Phase Check-In 2 | September 27, 2024 | |
Arbitrum RWA Analytics Dashboard - PYOR | Final Launch & Distribution | October 14, 2024 | |
Mystic Finance | Progress Update on Enabling Lending Market | September 13, 2024 | 100 |
Mystic Finance | Security Audit + Lending Market Update | September 13, 2024 | |
Mystic Finance | Enablement of Lending Market | October 11, 2024 | |
Mystic Finance | Program Update 1 | October 31, 2024 | |
Mystic Finance | Program Update 2 | November 29, 2024 | |
Mystic Finance | Program Update 3 | December 20, 2024 | |
Jia | Plan for Scoping & Pilot Development | August 26, 2024 | 100 |
Jia | Progress on Scoping & Pilot Development | September 13, 2024 | 100 |
Jia | Program Update 1 | September 30, 2024 | |
Jia | Program Update 2 | October 31, 2024 | |
Jia | Program Update 3 | November 29, 2024 | |
Jia | Program Update 4 | December 20, 2024 | |
Jia | Program Update 5 | January 31, 2025 | |
Jia | Program Update 6 | February 28, 2025 | |
Jia | Program Update 7 | March 31, 2025 | |
Jia | Program Update 8 | April 30, 2025 | |
Jia | Program Update 9 | May 30, 2025 | |
Jia | Program Update 10 | June 30, 2025 | |
Truflation | Finalize HEDGE Oracle Data Feed | August 26, 2024 | 100 |
Truflation | Update on Launching Hedge Index with Partner | September 13, 2024 | |
Truflation | Launch Hedge Index with Partner | September 30, 2024 | |
Truflation | Program Update 1 |
Find new product partner to launch new RWA product on Arbitrum | October 31, 2024 | | | Truflation | Program Update 2
Launch products with 2 new teams | December 20, 2024 | | | Infinfty | Program Update 1 | September 6, 2024 | 100 | | Infinfty | Program Update 2 | September 13, 2024 | 100 | | Infinfty | Program Update 3 | September 30, 2024 | | | Infinfty | Program Update 3 | October 31, 2024 | | | Infinfty | Program Update 4
Finish Deployment of Token Standard | November 29, 2024 | | | Infinfty | Program Update 5 | December 20, 2024 | | | Infinfty | Program Update 6 | January 31, 2025 | | | Infinfty | Program Update 7 | February 28, 2025 | | | Infinfty | Program Update 8 | March 31, 2025 | | | Infinfty | Program Update 9 | April 30, 2025 | | | Infinfty | Program Update 10